Bambarabatuoya MHPP
3.3MW
The Company’s first project Bambarabatuoya mini-hydro power project is sited in Bambarabatuoya, Ratnapura District.
This project was commissioned and connected to the National Grid in 2001. The company has a 15-year power purchase agreement with the Ceylon Electricity Board and contributes 12.33GWh of electricity to the national grid.
Project Specifications
Location | Ratnapura, Sri Lanka |
Design Flow | 8.9m3/s |
River Catchment | Kalu Ganga, Bambarabatuoya |
Effective Catchment Area | 76 km2 |
Head | 47m |
Channel Length | 2850m |
Plant Factor | 44% |
Penstock Length | 150m |
Commissioning Date | 1-Jun-01 |
Turbine Type | Francis Turbine ( 4 x 800kw) |
Project Cost | US $3MN |
Core Responsibilities of Vidullanka PLC | Lead Project Developer, Project Manager during Construction & Lead Operation Manager |