The Company's sixth project Wembiyagoda Mini Hydro Power Project is in Kalawana, Ratnapura District, Wembiyagoda. This project was commissioned in March 2013. The company has a 20-year power purchase agreement with the Ceylon Electricity Board and contributes 5.26 GWh of electricity to the national grid.
Technical Specification
Project Capacity
:
1.3 MW
Mean Annual energy supply
:
4.5 GWh
River catchment
:
Koswathu Ganga
Head
:
22.5 m
Channel Length
:
440 m
Penstock Length
:
40 m
Plant Factor
:
39.5 %
Commissioning Date
:
19 March 2013
Turbine Type
:
2 Francis machines @ 650 kW