The Company's fourth project Ganthuna Udagama mini hydro power project is sited in Ganthuna, Aranayake, Kegale District. This project was commissioned in March 2010. The company has a 20-year power purchase agreement with the Ceylon Electricity Board and contributes 4 GWh of electricity to the national grid.

Technical Specification
Project Capacity
:
1.2 MW
Mean Annual energy supply
:
4 GWh
River catchment
:
Gurugodaoya
Head
:
220 m
Channel Length
:
220 m
Penstock Length
:
560 m
Plant Factor
:
38 %
Commissioning Date
:
26 March 2010
Turbine Type
:
2 Units of Pelton Turbines @ 600 kW each